Hornsey Library
This project involved refurbishment of a listed building originally built in 1965.
Installation of new suspended ceilings, lighting, rewiring, alarm systems and redecorations throughout were carried out on a fast track programme completed in 18 weeks.
The works were undertaken while the library and ancillary offices remained operational, including access to the general public for the majority of the contract.